Projects in which a guarantee has been deposited (if applicable) for the access point and gird connection request, the connection request has been made (with the distribution company or transmission company) and at least 50% of the land rental contracts have been signed for where the plant is to be located.
Projects that have been granted access and gird connection permits by the distribution company or transmission company.
Projects that have been granted a favourable Environmental Impact Statement (DIA in spanish) by the competent body, this sub-classification is considered only for projects located in Spain to certify compliance with the milestone according to RDL 23/2020.
Projects that have obtained the Prior Administrative Authorisation (or equivalent permit depending on the country) from the competent body and have applied for the Construction Licence and Sectoral Permits.
Projects that have obtained all the necessary permits to be able to proceed with the construction of the projects, they have reached Ready to Build status.
Projects that that are either fully built and operational or in the administrative phase of the application for commissioning. The duration of this phase is the useful life of the plant.
Country | Early Stage | Grid Connection | Backlog | Under Construction | Operation | Total |
---|---|---|---|---|---|---|
Spain | 0 | 0 | 0 | 0 | 45 | 45 |
Italy | 0 | 0 | 0 | 0 | 0 | 0 |
Portugal | 0 | 0 | 0 | 0 | 0 | 0 |
France | 0 | 0 | 0 | 0 | 12 | 12 |
Poland | 0 | 0 | 0 | 0 | 34 | 34 |
Panama | 0 | 0 | 0 | 0 | 66 | 66 |
TOTAL ADX | 0 | 0 | 0 | 0 | 157 | 157 |
Country | Early Stage | Grid Connection | Environmental Approval | Backlog | Under Construction | Operation | Total |
---|---|---|---|---|---|---|---|
Spain | 0 | 0 | 6 | 210 | 62 | 110 | 388 |
Italy | 0 | 170 | 0 | 29 | 0 | 0 | 199 |
Portugal | 0 | 0 | 0 | 211 | 0 | 0 | 211 |
France | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Poland | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Panama | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
TOTAL ADX | 0 | 170 | 6 | 450 | 62 | 110 | 798 |
Country | Early Stage | Grid Connection | Environmental approval | Backlog | Under Construction | Operation | Total |
---|---|---|---|---|---|---|---|
Spain | 0 | 0 | 6 | 210 | 62 | 155 | 433 |
Italy | 0 | 170 | 0 | 29 | 0 | 0 | 199 |
Portugal | 0 | 0 | 0 | 211 | 0 | 0 | 210 |
France | 0 | 0 | 0 | 0 | 0 | 12 | 12 |
Poland | 0 | 0 | 0 | 0 | 0 | 34 | 34 |
Panama | 0 | 0 | 0 | 0 | 0 | 66 | 66 |
TOTAL ADX | 0 | 170 | 6 | 450 | 62 | 267 | 955 |