Portfolio of 2,498 MW, in different stages

The distribution of the portfolio of Audax Renovables, currently, by geographic area is as follows:



Early Stage => Connection point has been requested, and less than 50% of necessary land has been procured.
Grid Connection => The project has obtained grid connection, and at least 50% of the necessary land has been procured.
Backlog => Most of the permits have been requested.
Under Construction => The Project is in the stage of Ready to Build (RTB) or under construction.
Operation => The Project is operating.